Location |
Livno & Tomislavgrad, Canton 10, Bosnia and Herzegovina |
Capacity |
84MW (20×4.2MW) |
Generation |
259 GWh annually |
CO2 emssion reduction |
244 000 tons annually |
Construction start |
July 2022 |
Operation start |
Expected middle of 2024 |
Legal permits |
Environmental Permit, Energy Permit, Urban Permit, Construction Permit, Prior Approval for Connection obtained from competent ministries of FBiH |
Connection |
Connection Agreement with Elektroprijenos BiH signed |
Tariff & PPA |
Registration with OIEiEK completed |
Construction |
20 turbines hoisted |