On July 3, 2024, after completing the on-site inspection of the booster station of the Ivovik wind power project and strict review of relevant technical documents, a 9-membered acceptance committee of the Bosnia and Herzegovina State Grid Company Elektroprijenos BiH officially issued a decision, unanimously agreeing that the Ivovik wind power project passed the technical acceptance.
Technical inspection determines that a facility was built in accordance with the technical documentation on the basis of which the construction permit was issued, technical regulations and norms, as well as the conditions for the construction established by special regulations.
This means that the Ivovik project has met the technical requirements stipulated in the Grid Connection Agreement and has taken a big step towards achieving the goal of grid-connected power generation.
According to local power regulations, Elektroprijenos BiH, as the owner and manager of the national power grid, is responsible for the overall technical review of the design, equipment procurement, civil engineering and installation of facilities for grid connection.